DEVIATIONS TO THE
ESTIMATES
PREPARATION OF ESTIMATES
Estimate is the key document for any project.
Consists of:
Detailed Report on the project
Lead Statement
Rates for the items
Detailed Specifications
Detailed Measurements and Quantities
Abstract Estimate showing the total estimate cost
Drawings
PREPARATION OF ESTIMATES
While preparing estimate a detailed report to be made on
purpose of the project,
• necessity of the project,
benefits that will be achieved,
key parameters considered in most economical design,
detailed specifications,
method of financing, etc.
In case of a project consisting of several works, the detailed measurements and abstract estimates may conveniently be prepared for each work, supplemented by a General Abstract bringing all the estimates together
PREPARATION OF ESTIMATES
Detailed Estimates must be prepared before obtaining Administrative Sanction
Things to be considered during preparation of estimates:
Soil Characteristics for arriving at the type of foundation
Safe Bearing Capacity of Soil for structural designs
Alignment of Pipelines, Drains, Roads etc.
Considering the existing Infrastructure,
Parameters such as population, quantity of water required etc. in case of Water Supply project, Sullage/ Sewage to be discharged in case of UGD network, Storm Water to be discharged in case of Drains etc.
Plans, Drawings & Designs for arriving at possible quantities of items
PREPARATION OF ESTIMATES
Rates for items proposed in the Estimate
Lead Statement is the basic document from which the rates for individual materials i.e. Coarse Aggregates, Fine Aggregates, Bricks etc. is arrived
Lead i.e. Distance of source of material from the ULB is fixed by the R&B Department and is adopted in the estimates. The lead statement included in the estimate is to be approved by the Executive Engineer of the ULB or PH Division concerned.
Schedule of Rates is an Annual Document approved and published by the Board of Chief Engineers[BOCE] containing standard rates for all items collectively, which are to be adopted by all Engineering Departments in preparation of Estimates.
Government servants should treat the rate and cost amount arrived against each item in estimate and the abstract showing the total estimated cost of a work or part of a work as strictly confidential a a
All an
PREPARATION OF ESTIMATES
Provisions to be made in the Estimate
Statutory Taxes such as Goods & Service Tax @ 12% on Works Contracts, 18% on Supply Contracts/ Works Contracts that generates Revenue, 5% for works which contain predominantly earthwork
NAC @ 0.10%, Seigniorage Charges
Payments to be made towards inter-departmental charges i.e. NHAI, Railways, AP DISCOMS etc.
Provision towards APPMS @ 0.15%
Provision towards Price Adjustment
Provision towards unforeseen items (which are likely to be encountered during execution)
Revised Estimates - Likely Reasons
A Revised technical estimate must be submitted when the expenditure is likely to exceed the amount of sanctioned estimate.
A Workslip must be submitted as when deviations are found in the quantities of items proposed for execution or Items which are not proposed in the original estimate are to be taken up for execution.
A Workslip has to be formulated during the course of execution of work and the expenditure is well within the original administrative sanction amount
Deviation is a form of Workslip, but devloped after completion of the work (or) at the end of work and when no further variations are necessitated in the work.
Revised Estimates/ Workslip/Deviation must be accompanied by a report showing the progress made to date and explaining the cause(s) of the revision
Revised Estimates - Likely Reasons
Inadequate investigations in respect of Site conditions, alignment etc.
Changes in specifications of items
Improper estimating :
Preparation of estimates in a slipshad manner - Omission of important items of works Poor-estimation of Safe Bearing Capacity resulting in wrong choice of foundation. ► Mistakes in working out of quantities and rates of items of work Changes in Quarries and leads of materials
Change in design, alignment and scope of the Scheme
► Inclusion of new items which are not
iginally contemplated
Changes in Soil Specifications
Revised Estimates - Likely Reasons
Delay in execution of the project is one of the prime reason for Escalation in project cost due to
increase in prices
Land Acquisition costs
Due to conditions beyond the control of department for example:
Increase in cost of rising cost of works that are spread over a long period
Increase in schedule of rates on labour and materials
Increase in cost of controlled materials i.e. steel, cement, bitumen etc.
Increase due to change of foundation
Revised Estimates
- Remedial Measures
Deviations in the estimates should be kept to minimum, if not entirely eliminated
Deviations can be kept to minimum with thorough and detailed inspection of sites and should cover
The suitability of site
Suitability of foundation
Adequacy of design
Soils and materials (qualitative and quantitative) and leads
Soil classification
► Dewatering
Land acquisition etc.
Revised Estimates - Remedial Measures
The Departmental officials should inspect works before technical sanction is accorded by
competent authority as per the monetary limits indicated below:
Engineer-in-Chief/ Chief Engineer
Superintending Engineers
Executive Engineers
- Rs.2 Crs and above
- - Rs.0.40 Crs to Rs. 2 Crs.
- up to Rs. 0.40 Crs.
Revised Estimates - Approval
Without sanction from competent authority, expenditure in excess of provision or changes in scope of work should not be done.
The departmental officers have powers to accept the tenders and execute works with excess quantities only up to the limits specified.
If excesses are beyond their competency to approve, the revised estimates have to be sanctioned by Government.
Abuse of powers by departmental officers in incurring expenditure beyond the limit specified is an offense of serious nature.
Revised estimates must be submitted to competent authority for approval as soon as the excesses / deviations in the estimate are found necessary or unavoidable.
Excess expenditure should not be incurred without prior approval of competent authority.
Revised Estimates - Approval - Powers
Powers delegated to Engineers to accord excess over estimates as per G.O. 1007 T,R&B, Dt:05-11-1976
Government
Chief Engineer
Superintending Engineer
All excess of more than 15% of the amounts of original estimate sanctioned
All excess of not more than 15% of the amounts of original estimate sanctioned by him or by a higher authority i.e. E-n-C
All excess of not more than 10% of the amounts of original estimate sanctioned by him or by a higher authority.
The total amount of excess shall be within the limit of his powers to sanction estimates technically i.e. Technical Sanction
A S.E. has no power to sanction any excess over a revised estimate sanctioned by a higher authority
Revised Estimates - Approval - Powers
Powers delegated to Engineers to accord excess over estimates as per G.O. 1007 T,R&B, Dt:05-11-1976
Executive Engineer
All excess of not more than 5% of the amounts of original estimate sanctioned by him or by a higher authority.
The total amount of excess shall be within the limit of his powers to sanction estimates technically i.e. Technical Sanction
A E.E. has no power to sanction any excess over a revised estimate sanctioned by a higher authority
Revised Estimates - Approval - Powers
. The Govt. vide G.O. Ms. No. 504 M.A. & U.D. (A1) Dept., Dt:12-07-2007 issued orders approving Engineering, Procurement & Construction (EPC) system of procurement for implementation projects/works sanctioned with an estimated cost of Rs.10.00 Crores in all the ULBs costing expeditions completion of work.
the of for The Govt. constituted three (3) Committees to exercise the functions as shown below:
Committee-I
Committee-II Committee-III
Approval of Technical Parameters such as Scope, Objective & final deliverables of the Project, IBM/ deciding basic parameters/approval of live bid documents/evaluation criteria, payment schedule Approval of Technical Evaluation for opening of price bids Approval of extension of time beyond six months/ amount to be paid to the contractor for additional work / deviations for item. i) Not contingent to the main work. ii) Contingent but outside the scope of original contract
Revised Estimates - Approval - Powers
The Govt. vide G.O. Ms. No. 168 M.A. & U.D. (Budget) Dept., Dt:01-07-2016 constituted Members of Committee -III as follows:
Committee-III Approval of extension of time beyond six months/ amount to be paid to the contractor for additional work / deviations for item. i) Not contingent to the main work. ii) Contingent but outside the scope of original contract Members 1) Chief Engineer (PHMED), A.P. 2) Representative from MA&UD Department, A.P. 3) Representative from Finance Department, A.P. 4) Commissioner (ULB concerned) for ULB tenders. 5) Chief Engineer / Superintending Engineer/Executive Engineer of concerned ULB/SE(PH)
The Government vide G.O. Ms. No. 222 M.A. & U.D. (Budget) Department, Dated. 08.06.2017 have
issued orders to extent the guide lines in finalizing the tender for the Non-Engineering Procurement and Construction (Non - EPC) works also under similar analogy of the Government orders issued above for Engineering Procurement and Construction (EPC)Works.
O
•
IMPORTANT LITERATURE
Andhra Pradesh Public Works Department Code
Para No. 84, Para No. 112, Para No. 113, Para No. 154,
Andhra Pradesh Detailed Standard Specifications
G.O. 1007 T,R&B, Dt:05-11-1976
G.O. Ms. No. 504 M.A. & U.D. (A1) Dept., Dt:12-07-2007 G.O. Ms. No. 168 M.A. & U.D. (Budget) Dept., Dt:01-07-2016 ► G.O. Rt. No.668 M.A. & U.D. (Budget) Dept., Dt:10-07-2018
Revised Estimates
A Project with no (or) minimal revisions acts as a Key Performance Indicator of capabilities of any Engineer.
Minimum (or) No variations in estimates can be achieved by performing preliminary surveys and investigations at the inception stage of the project scrupulously, duly following all the Engineering Practices.
Closing the projects within the stipulated Time and Sanctioned Amount leads to financial discipline results in savings to the Govt. ex-chequer.
Published by ఇది వాస్తవం
Working ఫర్ society
View all posts by ఇది వాస్తవం